LAO 2004-05 Budget Analysis: General Government

Analysis of the 2004-05 Budget Bill

Legislative Analyst's Office
February 2004

Office of Emergency Services (0690)

The Office of Emergency Services (OES) is headquartered in a state-of-the-art command and control center in Sacramento County that was constructed in 2002. It also operates a Coastal Region Operations Center in Oakland, a Southern Region Coordination Center at Los Alamitos, a Specialized Training Institute at San Luis Obispo, and small field offices at other locations. The Governor's budget does not include any capital outlay funding for the office.

Although we have no issues with the budget, the 2003 infrastructure plan for the office includes two projects about which we have concerns. The OES infrastructure plan and these projects are discussed below.

Infrastructure Plan

The 2003 California Five Year Infrastructure Plan shows the OES identified almost $50 million in infrastructure needs (see Figure 1). Of this total, $40 million would replace two- operations centers. This figure also shows the capital outlay approved in the 2003-04 Budget Act and proposed by the current administration in the Governor's 2004-05 budget.

Figure 1

Office of Emergency Services
2003 Infrastructure Plan

(In Thousands)

 

2003-04

2004-05

2005-06

2006-07

2007-08

Total

Needs Identified by OES

Critical infrastructure
deficiencies

$1,631

$1,396

—

—

—

$3,027

Workload space deficiencies

1,291

5,937

$7,230

$28,490

$3,750

46,698

  Totals

$2,922

$7,333

$7,230

$28,490

$3,750

$49,725

Project’s Scheduled for Funding

Critical infrastructure deficiencies

$235

$1,396

—

—

—

$1,631

Workload space deficiencies

—

—

$3,000

$1,830

$22,095

$26,925

  Totals

$235

$1,396

$3,000

$1,830

$22,095

$28,556

Approved in 2003-04 and Proposed in 2004-05

  Totals

$235

—

—

—

— 

$235

Need for and Scope of Planned Operations Centers Unclear

We recommend that the office report at budget hearings on its current plans for replacing two operations centers.

Two projects identified by the department in its infrastructure plan need better definition of their programmatic need and the scope of the facilities required. These are: 

At this time, we are unable to evaluate the need for, and scope and cost of, either proposal. We recommend that the office report at budget hearings on its current plans for replacing these operations centers.


Return to Capital Outlay Table of Contents, 2004-05 Budget Analysis