August 21, 2007
Pursuant to Elections Code Section 9005, we have
reviewed the proposed initiative File No. 07‑0027, Amdt. #2-S, the
California Energy Independence and Zero Carbon Dioxide Emission
Electrical Generation Act of 2008.
Background
California’s “Moratorium” on New Nuclear Power Plant Development
Since 1976, state law has conditioned the
permitting of new nuclear power plants in the state upon the finding by
the California Energy Resources Conservation and Development Commission
(the “California Energy Commission” or “CEC”) that the federal
government has identified and approved a demonstrated technology for:
In effect, these two conditions have created a
moratorium on the construction of new nuclear power plants in California
as neither of these conditions has been met. The federal government has
not approved a demonstrated technology for the reprocessing of nuclear
fuel rods. And, while the federal administration has recommended to
Congress the Yucca Mountain site in the Nevada desert as a potential
permanent disposal site for nuclear waste, there remain political and
legal obstacles to use of the site for this purpose. These obstacles
include, among others, concerns expressed by the state of Nevada about
adverse groundwater impacts. Accordingly, no new nuclear plants have
been constructed in California in more than 30 years.
Despite the statutory conditions that have
prevented new nuclear power plant development, nuclear power provides
15 percent of California’s electricity supply. The statutes that in
effect created California’s moratorium specifically “grandfathered” two
preexisting nuclear power plants—the Diablo Canyon Power Plant near San
Luis Obispo and the San Onofre Nuclear Generating Station in San
Clemente—and both facilities continue to operate today. In addition, a
third plant near Phoenix, Arizona—the Palo Verde Nuclear Generating
Station—supplies California with electricity and is partially owned by
several California public utilities. Without access to a permanent
disposal site for nuclear waste, these facilities temporarily store
their nuclear waste on site, either in water or in “dry case” cement
casings.
Regulation of Nuclear Power Plants in California
Both the federal and state
governments regulate nuclear power plants. In order to operate, nuclear
power plants must have a license from the federal Nuclear Regulatory
Commission (NRC). In setting standards for these facilities, NRC focuses
on safety issues, including seismic safety and prevention of radiation
hazards. Case law has established that while states are preempted by the
federal government from regulating the safety aspects of nuclear power
plants, states have the authority to regulate such plants based on
economic and environmental concerns.
In California, several state agencies and local
governments have regulatory authority over particular aspects of nuclear
power plant development and operation. The CEC, as the state’s primary
energy planning agency, is responsible for permitting the siting and
operation of nuclear power plants. Other relevant state agencies can
include—largely depending on the location of the plant and the nature of
pollution created—the Regional Water Quality Control Boards, which issue
permits for the discharge of pollutants into the state’s waters; the
California Coastal Commission, which regulates coastal development and
issues development permits relative to coastal energy plant siting which
the CEC generally must adopt; the California Public Utilities
Commission, which advises CEC on nuclear plant siting and allocates a
plant’s costs among ratepayers when an investor-owned utility is the
plant owner; the California State Lands Commission, which issues permits
for private use of the state’s public resources; the state Department of
Fish and Game, which regulates matters related to endangered species;
and the Department of Toxic Substances Control, which regulates
hazardous materials storage and release. In addition, local governments,
in exercising their local land use authority, regulate matters relevant
to nuclear power plant development, such as transmission line placement.
State and Local Emergency Planning and Preparedness
Nuclear power plants present potential safety and
security risks generally not associated with other types of
energy-generating facilities. Unlike other types of power plants, each
nuclear power plant contains large quantities of radioactive material
which, if released—through natural disaster, human error, or malicious
intent—may cause widespread public harm.
California state and local governments spend
money to plan for and respond to potential radiation releases. At the
state level, the Governor’s Office of Emergency Services Radiological
Preparedness Unit (RPU) assists, trains, and
conducts exercises with other state and local agencies and with nuclear
power plant operators to prepare to respond to a radioactive release.
The RPU also plans emergency response to an accident resulting from the
transportation of radioactive materials, such as nuclear waste. In
addition, counties in which active nuclear power plants operate—San
Diego County (the San Onofre Nuclear Generating Station) and San Luis
Obispo County (Diablo Canyon Power Plant)—maintain emergency
preparedness plans in case of radioactive release from the plants.
Proposal
The measure has three major sets of provisions:
Repeals Existing Statutory Moratorium on
Nuclear Power Plant Development. First, the measure repeals the
two above-noted statutory conditions that have, in effect, created a
moratorium on the construction of nuclear power plants in California
since 1976.
Provides New Conditions for Nuclear Power
Plant Development. Second, the measure establishes new siting
requirements for nuclear power plants to be administered by CEC. The
measure specifically prohibits CEC from certifying a site for a nuclear
power plant if the site is seismically active, as defined by the
measure. The measure also prohibits CEC from certifying a site for a
plant that uses a “once-through” cooling system, if the site either is
within five miles of a coastal area of biological significance as
determined by the State Water Resources Control Board or if the coolant
outflow is to a navigable river.
Makes Declarations About Methods to Store
Nuclear Waste. Finally, the measure also specifies that CEC is
to consider any cement casing or other “dry-cask” storage system
approved by NRC an appropriate method for storing nuclear waste for up
to 100 years.
Fiscal Effect
State and Local Regulatory Costs
To the extent that the measure results in new
applications to construct and operate new nuclear power plants in
California, the state would face administrative costs connected with the
regulation of the plants. As would be the case with any application to
develop a power plant under the jurisdiction of CEC (namely, thermal
power plants of 50 megawatts or greater), CEC would need to review the
siting of each proposed nuclear power plant and decide whether to
license the plant for construction and operation. On average, it
currently costs CEC $700,000 to $800,000 for each power plant siting and
licensing review it conducts, and roughly $15,000 in annual costs to
monitor compliance at a single power plant. The CEC’s costs to review a
proposed nuclear power plant could exceed these average costs because,
for example, of the greater public comment and legal challenges
potentially associated with developing nuclear power plants. In any
case, CEC has the authority to recoup its administrative costs through
siting fees and a ratepayer-funded special fund that funds the majority
of its state operations. The CEC currently receives no General Fund for
support of its operations.
Largely depending on the proposed location of the
nuclear power plant under consideration, there may be additional
administrative costs at several other state agencies to process
environmental-related permits that must be obtained by an applicant
proposing a new nuclear power plant and to enforce those permits during
operation. It is likely that the administrative costs of any other
affected agency would be less than CEC’s administrative costs, given the
narrower scope of review and oversight of those agencies. In addition,
most of these agencies have authority to recover through fees much, if
not all, of their administrative costs for permitting and enforcement
activities. To the extent that administrative costs to these other
agencies are not recouped from fees, the state General Fund could face
pressure to fund some of these costs.
Similarly, local governments would face unknown
administrative costs associated with their regulation of land use as it
relates to the proposed siting of a nuclear power plant within their
geographic area of jurisdiction. These costs are at least partially
recoverable through fees.
The total state and local administrative
costs that would result from the measure is unknown and would depend on
the number of new nuclear power plants that would be proposed for
development as a result of the measure. It is uncertain how many
applications for new nuclear power plants would be triggered by the
lifting of the current statutory conditions on the permitting of such
power plants. This is due to a number of other potential obstacles.
These potential obstacles include difficulties obtaining financing for
construction costs that can easily exceed $5 billion for a typical
plant. Other potential hurdles include the multiple state and federal
regulatory approvals that would be required; the local political support
for a plant siting that would be needed; and the transmission
infrastructure to connect a power plant to the state’s transmission grid
that might need to be developed. Given these significant potential
hurdles, it is possible that there would be only a few, if any,
applications over the next several years for new nuclear power plants,
should the measure pass.
State and Local Emergency Planning and Preparedness Costs
Both state and local governments would face
increased emergency preparedness costs, to the extent additional nuclear
power plants were built as a result of the measure. Any local county
government, however, would face increased costs related to emergency
preparedness only if a nuclear power plant were constructed within or
adjacent to a given county. Costs to the state would depend on the
extent to which new plants were built in areas currently not receiving
nuclear power-related emergency preparedness assistance from the state.
In any event, existing state law requires that a utility—including a
municipally-owned utility—operating a nuclear power plant provide state
and local authorities with funding for facility-related emergency
planning to the extent those costs are not covered by federal funds.
Therefore, any additional state or local emergency preparedness costs
resulting from the measure would be recovered from the plant
operator(s).
State Financial Exposure
The state may face two significant fiscal
pressures related to the measure. First, as is the case with other
facilities that generate pollution, there will need to be active
management of the pollution generated by any nuclear power plant
developed as a result of the measure, both during the plant’s operation
and after its closure. The state could be exposed to substantial costs
to clean up radioactive contamination or other pollution at operating or
closed nuclear power plants should the plant operators not have the
resources to pay the cleanup costs. At a single site, these cleanup
costs could be in the millions of dollars, based on the federal
experience with such costs at a federal facility.
Second, the state
could be exposed to substantial costs as a result of a major release of
radiation from a nuclear power plant resulting from a natural disaster,
accident, or malicious intent. While federal law requires operators of
nuclear power plants to pay into an insurance pool to cover some of the
costs resulting from a radioactive incident, this insurance is estimated
to provide only about $10.8 billion in coverage per radioactive
incident. Congress maintains responsibility to determine how to pay for
damages beyond this amount and federal law provides nuclear power plant
operators immunity from liability beyond the insurance requirements.
Absent subsequent action by Congress, the state might be exposed to
substantial financial risks, potentially in the billions of dollars,
should a major radioactive release occur at a nuclear power plant.
Economic Impacts
To the extent the measure spurs investments in
nuclear power production in the state, there are several types of
economic impacts that could result. These would include both impacts
directly associated with the investment activities themselves and
impacts relating to the effects of such investments on power production,
availability, and prices.
Direct Effects. With regard to
impacts associated with nuclear investments per se, such activity will
generate jobs, capital purchases, and other economic activities which in
turn will potentially increase state and local revenues through
increased personal income, corporation, sales, and property taxes. This
is especially so, given the large upfront capital costs required to
build nuclear power facilities. The magnitude of these effects will
depend both on the total amount of nuclear investments undertaken and
whether such investments merely substitute for other types of
energy-related investments or represent a net increase in such
investments. Although nuclear investments will be attractive if they are
deemed to have a sufficiently high expected economic rate of return,
both the nature and timing of the nuclear investments that would occur
is difficult to predict, given the complexities of the technology
involved, the many years that it takes to plan and build power plants,
and the myriad of factors that would be involved in making investment
decisions. These would include projections about future-year supplies
and costs of competing energy sources and, given the large volumes of
capital funds that would have to be borrowed, future financial
conditions such as interest rates. Given this, the likely amount and
impacts of such investments that would occur is unknown.
Other Effects. To the extent that
nuclear investments occurred and had the net effect of increasing the
amount and reliability of power, and/or lowered its price (such as due
to its effects on energy supplies and nuclear power generation’s lower
operating costs), this would have positive economy-wide effects in such
areas as lower production costs, higher output, more jobs, and increased
corporate profits. These, in turn, would potentially increase state and
local revenues through increased personal income, corporation, sales,
and property taxes. In addition, these factors could directly reduce
costs incurred by the state and local governments for their own
operations. The likely magnitude of these various other effects,
however, is unknown.
Summary
-
Potential, unknown state and local administrative costs,
largely paid for by fees, for review of new power plant applications and
for regulatory enforcement and emergency planning related to new power
plant construction and operation.
-
Potential, unknown financial exposure to the state in the
long term, potentially in the millions of dollars in environmental
cleanup costs at each new nuclear power plant site, and potentially in
the billions of dollars in the event of a major radioactive release.
-
Potential, unknown increase in state and local revenues in
the long term, to the extent the measure generates new investment in the
state in the nuclear power industry that is not fully offset by
decreased investment in other energy sectors.
Return to Initiatives and Propositions
Return to Legislative Analyst's Office Home Page