January 2020
University of California Capital Outlay Projects
(In Thousands)
2020-21 | All Years | |||||
Campus | Project | Phases | State Cost | State Cost | Total Cost | |
Renovation | ||||||
San Diego | Meyer Hall and York Hall seismic renovation | C | $52,158 | $52,158 | $54,408 | |
Berkeley | Stephens Hall seismic renovation | P,W,C | 46,870 | 46,870 | 46,870 | |
Berkeley | Wellman Hall seismic renovation | P,W,C | 43,793 | 43,793 | 43,793 | |
Davis | Social Sciences and Humanities Building seismic renovation | P,W,C | 33,400 | 33,400 | 33,400 | |
Los Angeles | Public Affairs Building seismic renovation | C | 25,000 | 25,000 | 28,800 | |
Davis | Voorhies Hall seimsic renovation | P,W,C | 24,200 | 24,200 | 24,200 | |
Davis | Young Hall seismic renovation | P,W,C | 23,800 | 23,800 | 23,800 | |
Berkeley | Durant Hall seismic renovation | P,W,C | 20,010 | 20,010 | 20,010 | |
Santa Barbara | Music Building Unit 1 seismic renovation | P,W,C | 15,000 | 15,000 | 15,000 | |
Davis | Jungerman Hall seismic renovation | P,W,C | 12,200 | 12,200 | 12,200 | |
Systemwide | Renovation of new Sacramento Learning Complex | C | 11,400 | 11,400 | 18,400 | |
Davis | Mann Laboratory seismic renovation | P,W,C | 5,670 | 5,670 | 5,800 | |
Berkeley | Moffitt Library seismic renovation | P,W,C | 5,327 | 5,327 | 5,327 | |
Irvine | Social Science Lecture Hall seismic renovation | D,C | 2,261 | 2,261 | 3,577 | |
Subtotals | ($321,089) | ($321,089) | ($335,585) | |||
Construction | ||||||
Riverside | New School of Medicine Building | W,C | $93,600 | $100,000 | $100,000 | |
Maintenance | ||||||
Systemwide | Deferred maintenance | C | $35,000 | $35,000 | $35,000 | |
Other | ||||||
Systemwide | Various planning activities | P,W | $80,000 | $80,000 | $80,000 | |
Berkeley | Centennial Bridge relocation | C | 15,181 | 15,181 | 27,681 | |
Totals | $544,870 | $551,270 | $578,266 | |||
Notes | ||||||
Except Mayer Hall and York Hall, all previous phases were supported with nonstate funds. For Mayer Hall and York Hall, the working drawings phase ($4.5 million) would be supported by the proposed $80 million for various planning activities. Campus funds supported the campus's preliminary plans. | ||||||
On the university bonds supporting the projects, the annual debt service is estimated to be $44 million. | ||||||
D = design. P = preliminary plans. W = working drawings. C = construction. E = equipment. |